Nous joindre
X
Rechercher
Publicité

Ministry of Transport and Sustainable Mobility

Île-aux-Tourtes bridge: the Autorité des marchés publics draws up a poor assessment

durée 08h26
3 novembre 2023
ici

commentaires

ici

likes

 

vues

imprimante
Jessica Brisson
email
Par Jessica Brisson, Éditrice adjointe

Deficiencies in the management and planning of contracts, lack of documentation, communication problems, failure to comply with recommendations - in short, the Autorité des marchés publics (AMP) has drawn up a bleak picture of the Ministry of Transport and Sustainable Mobility (MTSM) contract management in the Île-aux-Tourtes bridge case.

In its latest report, published on Wednesday, the AMP highlighted a series of shortcomings in the management and planning of contracts for the maintenance and upkeep of the current structure of the Île-aux-Tourtes bridge.

As a result, MTSM was unable to carry out the necessary work in a timely manner. 

According to the report, the MTSM ignored some 35 notices indicating that the construction contractor, Roxboro Excavation Inc. was not complying with the manufacturer's recommendations, particularly with regard to mortar preparation.

Also according to the AMP report, on May 8, 2020, the Ministère gave the contractor the mandate to carry out maintenance work. Although the specifications called for the use of 400 liters of cementitious mortar, the AMP's examination revealed that the work was not carried out as required.

"However, from the very first preparation work, the quantity of mortar used reached 4,000 liters. Due to issues with the mortar preparation used, the 4,000 liters spread had to be removed. In all, 8,000 liters were needed to complete the work, resulting in an additional expenditure of $4.938 million, excluding the cost of the mortar," reads the 130-page document.

Among the other shortcomings noted by the AMP in the Île-aux-Tourtes bridge file are the lack of visits by the MTSM to the worksite, the lack of communication between the various stakeholders, the disappearance and non-reading of certain e-mails, the unavailability of certain documents, and more.

Roxboro Excavation Inc. is part of the consortium formed by Dragados Canada Inc. Roxboro Excavation Inc. and Construction DeMathieu Bard (CDB) Inc. and was awarded the contract to build the new infrastructure, scheduled for partial inauguration in 2026.

The full report is available at https://amp.quebec.

RECOMMANDÉS POUR VOUS


Publié à 6h00

Début des travaux sur la 34e Avenue à Saint-Zotique

La Ville de Saint-Zotique avise les usagers de la route de son territoire de la mise en place d'une entrave routière qui démarre ce lundi 18 août et qui s'étirera jusqu'au 5 septembre prochain sur la 34e Avenue.  Des travaux sont en cours sur cette artère en lien avec la réfection de la piste cyclable située entre la rue Principale et la 37e ...

Publié le 15 août 2025

Passerelle multifonctionnelle: adoption d'un règlement d'emprunt à la hausse

La construction d’une passerelle multifonctionnelle au-dessus de l’autoroute 30 longeant le boulevard de la Cité-des-Jeunes coûtera 2 360 000$ plus cher que prévu à la Ville de Vaudreuil-Dorion. C’est ce qui a été annoncé lors de la séance régulière du conseil municipal tenue ce jeudi 15 août. « Même si nous adoptons le règlement d'emprunt ce ...

Publié le 14 août 2025

Travaux de pavage en cours aux Cèdres

Des travaux de pavage sont en cours sur le territoire de la Municipalité des Cèdres. Plus spécifiquement, la machinerie prend place sur les rues de l’Hôtel de Ville, des Émeraudes et des Rubis. Ces chantiers devraient se terminer le 21 août prochain.  Sur de l'Hôtel de ville, les opérations ont débuté le mardi 12 août, tandis que ceux sur les ...

app-store-badge google-play-badge