Île-aux-Tourtes bridge: the Autorité des marchés publics draws up a poor assessment

durée 08h26
3 novembre 2023
ici

commentaires

ici

likes

imprimante
Jessica Brisson
email
Par Jessica Brisson, Éditrice adjointe

Deficiencies in the management and planning of contracts, lack of documentation, communication problems, failure to comply with recommendations - in short, the Autorité des marchés publics (AMP) has drawn up a bleak picture of the Ministry of Transport and Sustainable Mobility (MTSM) contract management in the Île-aux-Tourtes bridge case.

In its latest report, published on Wednesday, the AMP highlighted a series of shortcomings in the management and planning of contracts for the maintenance and upkeep of the current structure of the Île-aux-Tourtes bridge.

As a result, MTSM was unable to carry out the necessary work in a timely manner. 

According to the report, the MTSM ignored some 35 notices indicating that the construction contractor, Roxboro Excavation Inc. was not complying with the manufacturer's recommendations, particularly with regard to mortar preparation.

Also according to the AMP report, on May 8, 2020, the Ministère gave the contractor the mandate to carry out maintenance work. Although the specifications called for the use of 400 liters of cementitious mortar, the AMP's examination revealed that the work was not carried out as required.

"However, from the very first preparation work, the quantity of mortar used reached 4,000 liters. Due to issues with the mortar preparation used, the 4,000 liters spread had to be removed. In all, 8,000 liters were needed to complete the work, resulting in an additional expenditure of $4.938 million, excluding the cost of the mortar," reads the 130-page document.

Among the other shortcomings noted by the AMP in the Île-aux-Tourtes bridge file are the lack of visits by the MTSM to the worksite, the lack of communication between the various stakeholders, the disappearance and non-reading of certain e-mails, the unavailability of certain documents, and more.

Roxboro Excavation Inc. is part of the consortium formed by Dragados Canada Inc. Roxboro Excavation Inc. and Construction DeMathieu Bard (CDB) Inc. and was awarded the contract to build the new infrastructure, scheduled for partial inauguration in 2026.

The full report is available at https://amp.quebec.

RECOMMANDÉS POUR VOUS


Publié le 2 avril 2026

Fermeture complète de la route Harwood dès le 8 avril

La Ville de Vaudreuil-Dorion informe la population qu’une fermeture complète de la route Harwood (route 342), entre la rue Henry-Ford et le chemin de la Petite-Rivière, sera en vigueur à compter du 8 avril pour une durée approximative de six semaines.  Cette entrave est requise afin de permettre la réparation du pont ferroviaire appartenant au ...

Publié le 1 avril 2026

Fermeture d'une portion de la Montée du Comté dès le 1er avril

La Municipalité des Coteaux avise ses citoyens et usagers de la route qu'en raison d'un bris d'égout survenu au 186 Montée du Comté, cette rue sera fermée à la circulation dès le mercredi 1er avril, et ce, pour une durée indéterminée.  Le secteur fermé est situé entre les rues Adrien-Rouleau et 338. Les usagers de la route concernés devront ...

Publié le 30 mars 2026

Une entrave à prévoir sur le boulevard de la Gare à Vaudreuil-Dorion

La Ville de Vaudreuil-Dorion avise les usagers de la route de son territoire de la mise en place d'une entrave à l'intersection du boulevard de la Gare et du boulevard de la Cité-des-Jeunes. Celle-ci est requise par Hydro-Québec et sera en place le lundi 30 mars.  Elle aura lieu dès 9h et sera en place jusqu'à 14h. Durant cette période, la voie ...

app-store-badge google-play-badge