The projected work schedule for the 4 streets is as follows:
- Week of August 14: preparatory work;
- Week of August 21: pulverization of existing pavement and street levelling;
- Week of August 28: paving of streets (2 layers) and installation of speed bumps;
- Week of September 4: driveway repairs and gravel resurfacing of shoulders;
- Week of September 11: pavement marking;
Emergency and fire services will be able to use the streets in case of intervention.